Supply of the main and auxiliary equipment of the CHP for the enterprise for the production of electric and thermal energy (electric power 2,145 MW, thermal power 2,268 MW).

Composition of the main equipment:

3 x MTU 20V4000L33/GB2145N5 - gas piston unit with an electric capacity of 2145 kW.

Scope of works:
- Technology project design
- Equipment delivery
- Installation supervision
- Engineering services