CHP for greenhouse complex for growing raspberries. The installed electric capacity is 1 MW based on the MTU 8V4000L64 gas piston unit with a single electric capacity of 1013 kW. The equipment operates in an island isolated network for artificial illumination purposes. IEC Energy uses its own know-how: an intelligent control system for lighting and energy flows of generators for reliable and uninterrupted power supply of greenhouse lighting systems in isolated systems.
Scope of works:
- Technology project design
- Equipment delivery
- Installation supervision
- Engineering services
- Commissioning works